Facilities Master Plan · Fall 2026

Respecting our history.
Preparing for our next century.

A focused, financially responsible plan to renew the Clubhouse, shaped by what Members told us after the last proposal.

Special Meeting & Vote Thursday, October 29, 2026
+45%Membership growth since 2018, from 520 to 750 Members
350Seated guests in the new, divisible Event Space
2New private dining rooms, both larger than the Fireside Room
$15.07MTotal estimated Phase 1 cost, including a $700K contingency

Our Mission

To create an atmosphere of recreation, fun, and camaraderie for our Members, with a sustained commitment to quality, outstanding facilities, and personalized service that anticipates and satisfies. When our Members are treated properly, the Club will be at its best.

Our Vision

  • A golf course with locally and nationally recognized conditions and a prestigious standing in Pennsylvania
  • A culture that encourages Members to broaden their involvement and deepen their passion for their Club
  • Repeatedly exceed the dining expectations of our Members, families, and guests
  • Continually reinvest in the Club responsibly to guarantee its value for generations to come
  • Execute all business dealings with respect and dignity
  • A positive work environment with training and career opportunities for all associates
  • Positive contributions to our community and to environmental sustainability

From Club Leadership

We listened. This plan is the result.

Two years ago, a proposal did not receive the support needed to move forward. The Board and the Long Range Planning Committee went back to work on a more focused, practical, and financially manageable approach.

Dear Fellow Kahkwa Club Members,

Several years ago, the Board of Governors recognized the urgent need for significant updates to our Clubhouse and related facilities. The original building is more than a century old, and while it remains an important part of Kahkwa's history and character, its aging infrastructure and outdated design can no longer fully meet the evolving needs of today's Membership.

Two years ago, a proposal presented to the Membership did not receive the level of support needed to move forward. The Board listened carefully to the concerns expressed and returned to the planning process with a commitment to develop a more focused, practical and financially manageable approach.

Working with the General Manager, the Board formed a diverse committee representing multiple areas of the Membership, including Members with professional experience in architecture, construction, accounting and banking. The committee thoroughly evaluated the entire facility and created a responsible long-term plan to guide the Club's investments over the next 15 to 20 years.

The broader Master Plan does not call for every improvement to happen immediately. It provides a framework for addressing the Club's needs in a coordinated manner and making responsible investment decisions over time.

The alternative would be to return to the Critical Needs Assessment completed in 2025, which identified approximately $4 million to $5 million in required work. That investment would address some immediate infrastructure concerns, but it would not correct the functional deficiencies that affect how the Clubhouse operates or how Members experience the Club today.

We hope you will see how seriously your previous feedback was considered, and that you agree this is a plan the Membership can support: one that respects Kahkwa's history while preparing the Club for a strong and promising future.

The Board of Governors

The Challenges

A Clubhouse built for a different era

The challenges facing Kahkwa are connected. An undersized kitchen affects dining and events. Inadequate storage creates inefficiencies throughout the building. Outdated furnishings and underused spaces shape the Member experience. Phase 1 addresses them together.

A growing Membership

Membership has grown almost 45% since 2018. The Clubhouse now carries more everyday dining, gatherings, private functions, holiday celebrations and weddings than it was designed for.

A kitchen stretched too thin

À la carte dining and private events share the same limited space, equipment and staff circulation. Phase 1 expands the kitchen in two directions, with a dedicated Member side and an event side.

A delivery area at the front door

Truck loading is highly visible from the main drive. Phase 1 moves it out of sight for a more welcoming first impression.

Nowhere to put things

Furnishings, supplies and event materials overflow into rooms throughout the Clubhouse. Phase 1 adds major storage beneath the Event Space and beside the private dining rooms.

Interiors at the end of their life

Decor and furnishings are about 20 years old. Locker rooms, second floor Guest Rooms and Offices all need renewal. The goal is not to change Kahkwa's character, but to renew it.

The best view, rarely seen

The Sunset Room has the Clubhouse's best views of the course and sunsets, yet most Members only see it at private events. Phase 1 makes it the everyday Grill.

Phase 1

Additions & Renovations to the Clubhouse

A coordinated renovation and expansion that addresses the Club's most immediate operational and Member needs while creating a foundation for future improvements.

Phase 1 site plan. The new Event Space and Golf Shop addition extends the Clubhouse to the west, beside the 1st tee.
01

Sunset Grill

The Ross Grill Room relocates into the Sunset Room, making its views part of everyday dining. A larger, modernized central bar lets the Club staff more efficiently. The patio remains a summer gathering space.

02

New Event Space

A new addition seats 350 for dinner, divides into two rooms with a bar for each, and has its own restrooms, golf course views, two outdoor patios and a separate guest entrance so events don't disrupt Member dining.

03

Two Private Dining Rooms

Built in the Georgian Room area, both larger than the current Fireside Room, for family dinners, meetings and celebrations, with more scheduling flexibility.

04

Expanded Kitchen

Expanded in two directions with a dedicated Member dining side and an event side, so both can run at full speed at the same time.

05

Locker Rooms, Guest Rooms & Offices

Men's and Women's Locker Rooms are modernized. Second floor Guest Rooms are renewed, strengthening an existing revenue source, and Offices become more functional.

06

Storage & Delivery

Significant new storage beneath the Event Space and beside the private dining rooms, plus a relocated delivery area out of sight of the arrival drive.

Event Space, Pro Shop and terraces to the west; expanded kitchen at the center; Upscale Dining, Private Dining Rooms and the Sunset Grill to the east; a new arrival and Member covered drop.

Sunset Grill Image is for concept only
Event Space Image is for concept only
Kahkwa course from above at golden hour

Phase 1 Summary

What Members will gain

  • A new Sunset Grill with a larger bar and the Club's best views
  • Two new private dining rooms
  • An expanded kitchen for Member dining and events
  • A new Event Space that can host large events to increase revenue
  • Renovated Men's and Women's Locker Rooms
  • Renovated Guest Rooms and Offices
  • New decor and furnishings throughout the Clubhouse
  • More storage for more efficient Club operations
  • A new delivery area to solve the current truck delivery issue

Construction Phasing & Schedule

Staged so the Club stays open

Work is sequenced to preserve as much Member access as possible. The golf course, Aquatics Center and Racquets Center stay open throughout.

  1. Members approve project
  2. Existing Clubhouse open for dining; events open all of 2027. Golf, Aquatics and Racquets open all of 2027.
  3. Architect completes Construction Documents
  4. Events & Golf Shop construction begins
  5. Locker Room renovations begin (complete April 2028)
  6. Clubhouse renovations begin. No events and limited dining through March.
  7. Event Space and Golf Shop complete. Member dining moves to the Event Space, Sports Bar, Patio & Terrace.
  8. Clubhouse construction completed
Phase 1Aug 2027 – May 2028Event Space & Golf Shop addition
Phase 2Oct 2027 – May 2028Lower level Locker Rooms
Phase 3Jan 2028 – Apr 2028Existing Kitchen & Bar
Phase 4May 2028 – Dec 2028Dining Room renovations
Phase 5Dec 2028 – Feb 2029Fitness Area renovations

During construction

  • The Clubhouse stays accessible to Members, in cars and on foot
  • The Clubhouse is open for dining all of 2027 and 2028
  • Event spaces are available all of 2027 and April through December 2028
  • Locker Rooms are open except October 2027 through March 2028
  • The Golf Shop operates from a temporary location during the addition

Clubhouse Renovation & Addition Planning Schedule

From Kuo Diedrich Chi Architects and BSI, as of 9/18/2026. Hover or tap a bar for its dates.

  • Planning & design
  • Permitting & pricing
  • Construction
  • Complete
  • Today

Programming & initial budget pricing (12/17/2025 to 6/18/2026) is complete and falls before the chart window.

Phasing plan approach: where each construction phase happens in the Clubhouse

The Long View

Facilities Master Plan

The Master Plan is the overall blueprint for the Club's future. It is shown here to explain how Phase 1 fits the larger vision. Approving Phase 1 does not commit Members to any future project. Each will be evaluated separately and brought to the Membership for approval.

  1. Arrival Drive / Centralized Parking

    Realigned Clubhouse arrival drive and a centralized parking strategy serving all Club needs. 530 spaces campus-wide.

  2. Clubhouse

    Renovation including the lower level, renovated Member spaces, enhanced kitchen service, a new Event Room wing with outdoor terraces, and a cart ramp with storage, charging and wash-down below.

  3. Golf

    New Pro Shop with cart ramp and storage, an indoor golf learning center with swing analysis bay and covered instructional tees, new bag-drop and expanded golf parking.

  4. Aquatics Center

    New zero-entry kid swim with shade structure, kid play area, bocce courts, refinished pool locker rooms.

  5. Racquets Center

    New indoor facility with 4 courts and Racquet Center, renovated outdoor courts, 6 pickleball courts maintained, new tennis parking.

  6. Maintenance

    Replace the failing maintenance barn with a new facility adjacent to golf for maintenance access.

Needs beyond Phase 1

Parking

Still inefficient; more spaces near the Clubhouse need continued planning.

Aquatics Center

Kitchen, locker room and kiddie area upgrades remain.

Racquets Center

Indoor facilities for year-round play will be explored.

Grounds Operations

A dedicated equipment and storage building is needed.

Finances

What it costs, and how it's funded

Project Cost

Estimated hard construction costs
Events & Golf Shop Addition$5,659,000
Clubhouse Renovations$3,865,000
Men's & Women's Locker Rooms$1,621,000
Guest Rooms & Offices$540,000
Site Work$442,000
Estimated Hard Costs$12,127,000
Estimated soft costs
Architectural & Engineering Fees$1,091,000
Furniture & Fixtures$750,000
Kitchen & Bar Equipment$400,000
Estimated Soft Costs$2,241,000
Total Hard & Soft Costs$14,368,000
Project Contingency$700,000
Total Estimated Project Cost$15,068,000

Funding Strategy

  1. Reset the existing capital structure. Repay the Club's existing debt ($680K at 8/31/26) and end the current capital assessment, giving the new program a clean start.
  2. Secure long-term project financing. A financial institution has indicated its willingness to finance the project, subject to final underwriting. Anticipated structure: a 10-year term with 15-year amortization. Final rate and terms are set near closing.
  3. Implement a new capital assessment, by membership category, below.

Monthly Capital Assessment

$200per month
$2,400per year

Replaces the current capital assessment. Begins upon Member approval. Repaid over the 10-year loan term.

All categories
Golf – Senior$200
Golf – Intermediate$185
Golf – Junior$175
Social – Senior$175
Social – Junior$165
Clubhouse$75
Non-Resident$25
Senior Limited Sports$200
Special Social$175
Corporate$200

Key cash flow assumptions

The financial model deliberately uses conservative assumptions. It does not rely on significant membership growth or immediate financial benefits from the renovation, and it tests the Club's ability to carry the project through construction and the full repayment period.

Membership Attrition

About 9% total, or 65 members, through 2028, mostly in social categories.

New Financing

About $15 million of new debt, 10-year term, 15-year amortization.

Construction Draws

Drawn as needed over the roughly 18-month build, not all at once.

Interest-Only Period

Interest-only payments for the first 12 months for added cash-flow flexibility.

Capital Assessment

Begins on Member approval, providing an immediate funding stream.

Event Revenue Disruption

About 0% reduction in 2027 and 10% in 2028, thanks to phased construction.

How Kahkwa compares

Initiation, monthly dues and monthly assessments at peer clubs in the region.

ClubInitiationDuesAssessmentNotes
The Kahkwa Club$15,000$750$48
Country Club of Buffalo$40,000$1,212$125 capital + $147 debt serviceWait list
The Park Club (Buffalo)$40,000$1,200$200
Nevillewood (PA)$60,000$1,475$150 capital + $150 debt service36-month wait list
Mayfield Sand Ridge (OH)$35,000$1,325$100
The Country Club (Cleveland)$100,000$1,500$40,000
Westwood Country Club$45,000$1,100$80
Canterbury Golf Club (Cleveland)$60,000$1,600$150
Kirtland Country Club (OH)$60,000$1,800$100

Figures as published in the Master Plan brochure. Kahkwa's assessment shown is the current capital assessment.

Voting Process

Your vote on Phase 1

Special Meeting · Thursday, October 29, 2026

After attending or reviewing the September 29 presentation and this plan, Members are asked to vote on Phase 1. A letter with notice of the meeting has been mailed to every Member.

1

Electronic Proxy

Vote in advance online. Complete the form only once. Closes October 28 at 6 p.m.

Kahkwa.com/MP
2

Paper Proxy

Included in the letter mailed to all Members. Complete it and return it to the Club before the October 29 meeting.

3

In-Person Ballot

If you attend the October 29 meeting and haven't voted in advance, a ballot will be available there.

Please use only one method of voting. Under the Kahkwa bylaws, there is one shareholder vote per membership.

Questions

Frequently asked questions

Why is Phase 1 needed now?

The original Clubhouse is more than a century old, and many of its spaces no longer meet the needs of today's Membership. Since 2018, Membership has grown from about 520 to 750, placing greater demands on the kitchen, dining areas, event facilities, locker rooms and storage. Phase 1 addresses these immediate functional needs while improving the everyday Member experience and creating opportunities for additional revenue.

What happens if Phase 1 does not move forward?

The Club would still need to address the aging infrastructure identified in the 2025 Facilities Assessment Report. Those repairs would handle certain immediate needs but would not solve the kitchen limitations, inadequate storage, outdated interiors or the strain of running Member dining and private events together. Members would still face an assessment, without the overall improvements in the plan.

What is the total cost, and how will the project be funded?

The total estimated cost of Phase 1 is $15 million. It will be funded through a bank loan repaid by Member assessments over a 10-year term. See Finances.

What will the Member assessments be?

They range from $25 to $200 per month depending on membership category. Use the assessment lookup to find yours.

What safeguards will help prevent cost overruns?

The contractor will meet regularly with the architect during the construction document phase and flag any design element that creates a budget concern so it can be adjusted before construction begins. The project includes a detailed construction budget, a $700,000 contingency and continuous oversight. Expenses and proposed changes are reviewed before approval, Members get regular updates on progress and spending, and the Club will hire an Owner's Representative to keep the project on schedule and within budget.

When will construction begin, and how long will it take?

If approved, construction is expected to begin in August 2027 and continue through December 2028, in sequence: the Event Space and Golf Shop addition first, then the Locker Rooms, Kitchen and Restrooms, Member dining areas, and second floor Guest Rooms and Offices. See the schedule.

Will the Clubhouse remain open during construction?

Yes. The Club intends to stay open throughout, with access to certain areas temporarily limited as work progresses. The initial addition runs from August 2027 through April 2028, and the existing Clubhouse remains accessible during that work.

How will construction affect dining, events and amenities?

The golf course, Racquets Center and Aquatics Center are expected to operate throughout. The Golf Shop will run from a temporary location while the addition is built. For much of 2028, Member dining will be offered in the Sports Bar, on the Patio and Terrace, and in the new Event Space when events are not scheduled.

How will the Club keep the project on schedule?

The contractor will follow a detailed schedule with defined milestones. A Project Manager and On-Site Superintendent coordinate the work and monitor daily progress, and an on-site Owner's Representative monitors the work on the Club's behalf and coordinates with the contractor and architect.

Who will oversee construction, spending and Member updates?

The Project Manager manages daily construction. The Owner's Representative provides additional oversight and serves as a direct link among the Club, contractor and architect. The Club will also set up a process for reviewing expenses, change orders and contingency use, and Members will receive regular updates.

Does approving Phase 1 commit Members to future Master Plan projects?

No. Approval of Phase 1 authorizes only the improvements and funding in this phase. Future projects will be evaluated separately based on need, cost and the Club's financial position at that time, and any additional improvements will be subject to Member approval.

Will Members who join after Phase 1 contribute to the cost?

Yes. New Members pay a prorated assessment and the applicable tiered initiation fee upon acceptance. Former Members who seek reinstatement within the 10-year period will also pay the assessment if they were Members when it was assigned.

Have another question about the Master Plan or Phase 1?

Consultants & Contributors

The team behind the plan

Kuo Diedrich Chi Architects

Planning & Architecture

An award-winning, full-service international architecture and design firm specializing in lifestyle design for clubs and resorts since 1994. They view extraordinary design as the outcome of effective listening, strong relationships and expertise.

BSI, Building Systems Inc.

General Contractor · PA, OH & NY

Erie's trusted general contractor since 1984, founded by the Schaaf family on a simple promise: do things the right way, all the time. A 100-person operation handling everything from service calls to $100M+ master plan developments.

David Laird Associates, Inc.

Civil Engineering

Land surveyors and civil engineers serving Erie, Meadville, Chautauqua and Jamestown since 1960, identifying boundaries, utilities and site issues before they become costly mistakes.

Kahkwa green framed by bunkers

A plan that honors Kahkwa's traditions

Over the past year, Members and committees from every area of the Club contributed their time, perspectives and expertise to this plan. The goal: a practical, financially responsible plan that addresses urgent needs while giving the Membership the greatest possible value for its investment.

We encourage every Member to review the proposal, ask questions and share feedback.

How to Vote